首页 > 新闻 > 正文

华星东方承建的福建省漳州北部片区垃圾焚烧发电项目烟气净化工程通过72+24小时试运行

时间:2021-10-29 13:57

来源:华星东方电力环保

华星东方电力环保承建的福建省漳州北部片区垃圾焚烧发电项目烟气净化工程于2021年10月8日通过72+24小时试运行。

The flue gas cleaning (FGC) project constructed by Huaxing East for waste incineration power plant in northern Zhangzhou, Fujian passed 72+24 hours trial operation on October 8, 2021.

image.png

该项目建设2×500t/d 焚烧炉+1×25MW 凝汽式汽轮发电机组。烟气处理采用旋转喷雾半干法脱酸+消石灰干法喷射+活性炭喷射+布袋除尘器+飞灰输送+低温SCR(预留)工艺,为我司EP工程。

The plant applied 2×500 t/d boilers and 1×25MW condensing turbine. The FGC consists of SDA semi-dry deacidification + lime dry injection + activated carbon injection + bag house filter + fly ash conveying + low temperature SCR (reserved). It’s an EP project of Huaxing East.

image.png

image.png

该项目为华星东方在漳州市,继上环投漳州一期,二期和瀚蓝集团漳州南项目后的第四个投产的烟气净化业绩。同时也奠定了华星东方在福建省的业绩领先地位,涵盖包括:漳州一期,二期,漳州南,晋江,安溪,石狮,建阳,福州,三明,上杭,霞浦等多个项目。

This project is the 4th operational FGC accomplished by Huaxing East in Zhangzhou, following the Zhangzhou project Phase I & II of Shanghai Environment Investment and Southern Zhangzhou project of Grandblue Group. Hence, Huaxing East has established its leading role in Fujian province in terms of FGC achievements which includ Zhangzhou Phase I & II, Southern Zhangzhou, Jinjiang, Anxi, Shishi, Jianyang, Fuzhou, Sanming, Shanghang, Xiapu, etc.

image.png

image.png

编辑:赵凡

  • 微信
  • QQ
  • 腾讯微博
  • 新浪微博

相关新闻

网友评论 人参与 | 条评论

版权声明: 凡注明来源为“中国水网/中国固废网/中国大气网“的所有内容,包括但不限于文字、图表、音频视频等,版权均属E20环境平台所有,如有转载,请注明来源和作者。E20环境平台保留责任追究的权利。

010-88480329

news@e20.com.cn

Copyright © 2000-2020 https://www.solidwaste.com.cn All rights reserved.

中国固废网 版权所有